The state of the bridge that was set for commissioning. By Martin AnguyoArua City The Resident City Commissioner of Arua, Salim Kumakech, has urged the public using the Ania culvert bridge in Ayivu West Division to remain calm as the contractor restructures th
The state of the bridge that was set for commissioning.
By Martin Anguyo
Arua City
The Resident City Commissioner of Arua, Salim Kumakech, has urged the public using the Ania culvert bridge in Ayivu West Division to remain calm as the contractor restructures the work.
Approximately two and a half weeks ago, Arua City leaders, led by the RCC, inspected the bridge, which was slated for commissioning, but found the work to be substandard.
Although they gave the contractor a one-week ultimatum to rectify the issues, little progress has been made since then. According to the RCC, the delay is attributed to the absence of the city accountant, who was out of the country on official duties, materials have been mobilized, they are also improving on the length of the road, and we believe by Wednesday, tangible result on the hot spots will have been resolved. Community should therefore help the government equally monitor public work, where they feel unsatisfied, they should let us know and we can abandon everything and first put our effort there? the RCC appealed.
However, the site supervisor Mr. Tom claims that, his role is limited to supervision and that he was not provided with adequate project documents, leaving him unable to take further action. "I can only supervise based on the documents and guidelines given to me," he explained. "Without proper documentation, I'm limited in what I can do to ensure the project meets the required standards. Mine was to supervise and I did my part and I am not even aware on whatever is supposed to be done there again" said the site supervisor.
The situation has raised concerns among the local community, who rely on the bridge for daily activities.
Erick Anguzu, a local boda boda rider, appealed to leaders to ensure timely supervision of projects handed to contractors. "We've seen many projects in this area being poorly executed," he said. "If leaders could closely monitor the progress, it would help prevent such issues."
The 30 million shilling infrastructure, constructed over Ania Lower Stream near Christ Church Ediofe, has drawn sharp criticism from locals who allege poor workmanship. Many are questioning the value for money and the impact of such projects on the community and as the contractor works to rectify the issues, the community remains hopeful that the final product will meet their expectations and serve the area well.